| Project: |
|
Church Street Underpass |
| Start Date: |
|
Early June, with completion in about 3 days. |
| Description: |
|
A 4" mill and new blacktop overlay. The underpass
will be closed to traffic. |
| Detour: |
|
A detour is planned. |
|
|
| |
| Project: |
|
Plover and Shaurette Streets - Plover Street from Division Street to Ellis Street and Shaurette
Street from Church Street to Division Street. |
| Start Date: |
|
April 14, 2008 with completion in August. |
| Description: |
|
Improvements include replacing the sanitary and storm
sewers, water main and reconstructing the street to the same width as before. The project will be closed to traffic
during construction. Division Street will be closed for approximately 2 week for sanitary sewer and water main
tie-ins.
See
the design change for the intersection of Plover/Shaurette/Division Streets.
224 kB File Requires Acrobat or Free Acrobat
Reader
See
a map of this project area. 36 kB File Requires Acrobat or Free Acrobat Reader |
| Detour: |
|
A detour is planned. No detour for Plover or Shaurette
Streets is planned. Division Street detour to be determined. |
| Assessments: |
|
Properties with clay sanitary sewer laterals and galvanized
water services will be special assessed to upgrade the old style services to new materials. |
| Contractor: |
|
Integrity Grading and Excavation Inc., Schofield, Wis.,
with a bid of $631,099. |
|
|
| |
| Project: |
|
Fourth Avenue - Fourth
Avenue from Second Street to west end (near Lee Street). Project may be shorted depending upon funding. |
| Start Date: |
|
Tentative start date is July. |
| Description: |
|
Improvements include replacing the sanitary and storm
sewers, water main and reconstructing the street. Fourth Avenue west of Frederick Street will be narrowed to meet
Americans with Disability Act (ADA) requirements at driveways and crosswalks.
See a map
of this project area. 44
kB File Requires Acrobat or Free Acrobat
Reader |
| Detour: |
|
None available at this time. |
| Assessments: |
|
Properties with clay sanitary sewer laterals and galvanized
water services will be special assessed to upgrade the old style services to new materials. |
| LRIP: |
|
A portion of the street paving will be paid for using
Local Road Improvement Program entitlement funds. |
|
|
| |
| Project: |
|
Patch Street Trail - Phase Two - Industrial Park Road from the Big Plover River bridge east
to Hoover Road Trail. |
| Start Date: |
|
May 5, 2008 with completion in July. |
| Description: |
|
A ten foot wide blacktop trail paralleling the south
side of Industrial Park Road. Work includes installing storm sewer, grading, curb and gutter, landscaping and street
improvements at Hoover. Other work includes painting and signing of the trail and bike lanes. All work will be
done under traffic except for a one week period to install curb and pave at the intersection of Hoover Road. Handicap
ramps and landscaping to finish phase one will be completed this spring as well.
See a map of
this project area. 38
kB File Requires Acrobat or Free Acrobat
Reader |
| Detour: |
|
A temporary truck route detour will be Leahy Av. to
Heffron St. |
| Assessments: |
|
Properties with clay sanitary sewer laterals and galvanized
water services will be special assessed to upgrade the old style services to new materials. |
| LRIP: |
|
A portion of the street paving will be paid for using
Local Road Improvement Program entitlement funds. |
|
|
| |
| Project: |
|
Commuter Trail under I-39 - Joerns Drive to Business Park Drive. WisDOT Project #6998-06-72. |
| Start Date: |
|
June, 2008 |
| Description: |
|
A ten foot wide blacktop trail from the east end of
Joerns Drive, under I-39, then south and east to Business Park Drive. The trail is made possible through a WisDOT
Transportation Enhancement Fund with 80%- 20% local matching funds.
See an
artistic rendering of the project. 250
kB File Requires Acrobat or Free Acrobat
Reader
See
project construction plans. 4.7 MB File Requires Acrobat or Free Acrobat Reader |
|
|
| |
| Project: |
|
I-39 Interchange (Exit 161) at Business 51. Interchange pavement replacement and bridge rehabilitation
project at Business 51 (Division St.) north of North Point Drive in Stevens Point. |
| Start Date: |
|
Improvements for the bridge will involve closing the
I-39 northbound exit and entrance ramps, from May
27 to August 29, 2008, at which time traffic
will be detoured via I-39, US 10, and Business 51. The I-39 southbound exit and entrance ramps will be closed for
approximately 3 weeks during the same time period. Repainting work on the structure will be done under traffic
through September.
Get
more information about this project from the WisDOT Web Site. |
| Description: |
|
Improvements include raising and replacing the concrete
bridge deck, repainting the steel bridge girders, replacing the ramp pavement and adding a deceleration lane for
the northbound I-39 exit ramp. |
| Detour: |
|
Traffic will be detoured via I-39, US 10 and Business
51.
See
a detour map on the WisDOT Web Site. |
| Contractor: |
|
American Asphalt of Wisconsin, Mosinee, WI with a bid
of $2.4 million. |
|
|
| |
| Project: |
|
I-39 Interchange (Exit 158) at US Hwy. 10. |
| Start Date: |
|
Project is scheduled for bid letting June, 2008. The
project is planned to start about the same time that Exit 161 (see above) opens, sometime in September with completion
in December. |
| Description: |
|
Improvements include adding two right turn lanes exiting
southbound I-39 at US 10 and lengthening the southbound deceleration lane onto US 10.
See
a map of this project area. 594 kB File Requires Acrobat or Free Acrobat Reader |
| Detour: |
|
To be determined. |
|
|
| |
| Project: |
|
US 10 Expansion Project - Stevens Point to Marshfield. |
| Description: |
|
The Wisconsin Department of Transportation (WisDOT)
began the initial phase of an estimated 234 million dollar multi-phase central Wisconsin transportation project
in 2006. The final phase is scheduled for completion in 2012. WisDOT is expanding 31 miles of US 10 between Stevens
Point and Marshfield. The new four lane facility will bypass the communities of Junction City, Milladore, Blenker
and Auburndale.
Get
more information about this project from the WisDOT Web Site.
WisDOT is Proposing Highway System Changes
As part of the US 10 highway expansion project, WisDOT is proposing jurisdictional transfers of some of our state
highways. Portions of existing US 10 and other state highways are expected to revert to local units of government.
Removal of US 10 from downtown Stevens Point west of I-39 and Wis. 66 from Stanley Street are part of the planned
changes to the state highway system.
See a map of
the proposed changes. 162 kB File Requires Acrobat or Free Acrobat Reader |
|
|
| |
Please slow down and drive extra carefully in construction
zones - give our crews a brake! Weather
and other factors can affect construction dates.
If you have questions or need more information,
call the Engineering Department
at 346-1561. |
| |