2008 Road Construction Projects

Project:   Church Street Underpass
Start Date:   Early June, with completion in about 3 days.
Description:   A 4" mill and new blacktop overlay. The underpass will be closed to traffic.
Detour:   A detour is planned.
 
Project:   Plover and Shaurette Streets - Plover Street from Division Street to Ellis Street and Shaurette Street from Church Street to Division Street.
Start Date:   April 14, 2008 with completion in August.
Description:   Improvements include replacing the sanitary and storm sewers, water main and reconstructing the street to the same width as before. The project will be closed to traffic during construction. Division Street will be closed for approximately 2 week for sanitary sewer and water main tie-ins.

See the design change for the intersection of Plover/Shaurette/Division Streets. 224 kB File Requires Acrobat or Free Acrobat Reader

See a map of this project area. 36 kB File Requires Acrobat or Free Acrobat Reader
Detour:   A detour is planned. No detour for Plover or Shaurette Streets is planned. Division Street detour to be determined.
Assessments:   Properties with clay sanitary sewer laterals and galvanized water services will be special assessed to upgrade the old style services to new materials.
Contractor:   Integrity Grading and Excavation Inc., Schofield, Wis., with a bid of $631,099.
 
Project:   Fourth Avenue - Fourth Avenue from Second Street to west end (near Lee Street). Project may be shorted depending upon funding.
Start Date:   Tentative start date is July.
Description:   Improvements include replacing the sanitary and storm sewers, water main and reconstructing the street. Fourth Avenue west of Frederick Street will be narrowed to meet Americans with Disability Act (ADA) requirements at driveways and crosswalks.

See a map of this project area. 44 kB File Requires Acrobat or Free Acrobat Reader
Detour:   None available at this time.
Assessments:   Properties with clay sanitary sewer laterals and galvanized water services will be special assessed to upgrade the old style services to new materials.
LRIP:   A portion of the street paving will be paid for using Local Road Improvement Program entitlement funds.
 
Project:   Patch Street Trail - Phase Two - Industrial Park Road from the Big Plover River bridge east to Hoover Road Trail.
Start Date:   May 5, 2008 with completion in July.
Description:   A ten foot wide blacktop trail paralleling the south side of Industrial Park Road. Work includes installing storm sewer, grading, curb and gutter, landscaping and street improvements at Hoover. Other work includes painting and signing of the trail and bike lanes. All work will be done under traffic except for a one week period to install curb and pave at the intersection of Hoover Road. Handicap ramps and landscaping to finish phase one will be completed this spring as well.

See a map of this project area. 38 kB File Requires Acrobat or Free Acrobat Reader
Detour:   A temporary truck route detour will be Leahy Av. to Heffron St.
Assessments:   Properties with clay sanitary sewer laterals and galvanized water services will be special assessed to upgrade the old style services to new materials.
LRIP:   A portion of the street paving will be paid for using Local Road Improvement Program entitlement funds.
 
Project:   Commuter Trail under I-39 - Joerns Drive to Business Park Drive. WisDOT Project #6998-06-72.
Start Date:   June, 2008
Description:   A ten foot wide blacktop trail from the east end of Joerns Drive, under I-39, then south and east to Business Park Drive. The trail is made possible through a WisDOT Transportation Enhancement Fund with 80%- 20% local matching funds.

See an artistic rendering of the project. 250 kB File Requires Acrobat or Free Acrobat Reader

See project construction plans. 4.7 MB File Requires Acrobat or Free Acrobat Reader
 
Project:   I-39 Interchange (Exit 161) at Business 51. Interchange pavement replacement and bridge rehabilitation project at Business 51 (Division St.) north of North Point Drive in Stevens Point.
Start Date:   Improvements for the bridge will involve closing the I-39 northbound exit and entrance ramps, from May 27 to August 29, 2008, at which time traffic will be detoured via I-39, US 10, and Business 51. The I-39 southbound exit and entrance ramps will be closed for approximately 3 weeks during the same time period. Repainting work on the structure will be done under traffic through September.

Get more information about this project from the WisDOT Web Site.
Description:   Improvements include raising and replacing the concrete bridge deck, repainting the steel bridge girders, replacing the ramp pavement and adding a deceleration lane for the northbound I-39 exit ramp.
Detour:   Traffic will be detoured via I-39, US 10 and Business 51.

See a detour map on the WisDOT Web Site.
Contractor:   American Asphalt of Wisconsin, Mosinee, WI with a bid of $2.4 million.
 
Project:   I-39 Interchange (Exit 158) at US Hwy. 10.
Start Date:   Project is scheduled for bid letting June, 2008. The project is planned to start about the same time that Exit 161 (see above) opens, sometime in September with completion in December.
Description:   Improvements include adding two right turn lanes exiting southbound I-39 at US 10 and lengthening the southbound deceleration lane onto US 10.

See a map of this project area. 594 kB File Requires Acrobat or Free Acrobat Reader
Detour:   To be determined.
 
Project:   US 10 Expansion Project - Stevens Point to Marshfield.
Description:   The Wisconsin Department of Transportation (WisDOT) began the initial phase of an estimated 234 million dollar multi-phase central Wisconsin transportation project in 2006. The final phase is scheduled for completion in 2012. WisDOT is expanding 31 miles of US 10 between Stevens Point and Marshfield. The new four lane facility will bypass the communities of Junction City, Milladore, Blenker and Auburndale.

Get more information about this project from the WisDOT Web Site.

WisDOT is Proposing Highway System Changes

As part of the US 10 highway expansion project, WisDOT is proposing jurisdictional transfers of some of our state highways. Portions of existing US 10 and other state highways are expected to revert to local units of government. Removal of US 10 from downtown Stevens Point west of I-39 and Wis. 66 from Stanley Street are part of the planned changes to the state highway system.

See a map of the proposed changes. 162 kB File Requires Acrobat or Free Acrobat Reader
 
Please slow down and drive extra carefully in construction zones - give our crews a brake! Weather and other factors can affect construction dates.

If you have questions or need more information, call the Engineering Department at 346-1561.
 