Prentice St. Reconstruction Project
The project will involve replacing old sanitary sewers, storm sewers, water mains, and reconstructing the street including curb, gutter and sidewalks from Maria Drive to College Avenue.

The project will be done in two phases to reduce the inconvenience to residents along the construction corridor. Phase One will be from Maria Drive to Fourth Avenue and Phase Two will be from Fourth Avenue to College Avenue.

The project is anticipated to begin in May and be substantially completed by mid-October, 2017. As always, the weather may dictate how soon construction crews can begin and complete their work.

Resources
See the following documents for more information about this project:

To receive notices via email and/or text message whenever news stories regarding road construction and street closings are posted here, go to our Notify Me Module and sign up for the "Road Construction" News Flashes. News and announcements from this site are also posted on our Facebook Page and Twitter Feed.

Contact
Director of Public Works
1515 Strongs Ave.
Stevens Point, WI 54481
Ph: (715) 346–1561
Email

Office Hours
Monday - Friday
7:30 am - 4:00 pm



News Flash - View All
Isadore St. Reconstruction Project to Begin Monday, July 9
Crews will begin work on Isadore St. at the intersection with Portage, working north to Fourth. Work will then continue north towards Maria. Isadore will be closed to through traffic for the duration of the project, until late October, weather permitting.
Division St. & North Point Dr. Intersection Closed June 7 - Aug. 30
American Asphalt closed the Division St. (Business 51) and North Point Dr. intersection on Thursday, June 7. Both ramps from I-39 to Division St. are closed. The closure is expected to last until August 30, 2018. Read More
Bottom
City of Wonderful Water
City of Stevens Point, 1515 Strongs Ave., Stevens Point, WI 54481 | Phone 715-346-1569